The County of Anoka is seeking a contractor to expand its data center by adding a second Uninterruptable Power Supply (UPS) unit. The bid was awarded to Sturgeon Electric Company with a base bid of $152,950. The project requires the contractor to provide all necessary materials and labor to complete the work. The bid documents and addendums are available for download on the County's website. Key aspects of the project include:
• The addition of a second UPS unit to the data center
• The provision of all necessary materials and labor to complete the work
• The requirement for the contractor to attend a pre-bid conference
• The availability of bid documents and addendums on the County's website