The City of Keene, New Hampshire, has awarded a contract to Project Resource Group, LLC, for the Keene Transfer Station Generator Project. The project involves the construction of a generator at the Keene Transfer Station/Recycle Center. The contract includes the provision of all materials, supplies, tools, equipment, labor, and services necessary for the construction and completion of the project. The contract price is $646,107.00, and the project is expected to be completed by March 16, 2018. The contract includes provisions for payment, changes to the work, and termination. Some key points about the job's work and scope-of-work include: the generator will be a biodiesel prime generator, the fuel storage tank will be a 12,000-gallon double-wall tank, and the project will include electrical site work and conduit installation.
• The contract includes a payment bond and a performance bond to ensure the contractor's obligations are met.
• The contractor is required to provide certificates of insurance and to maintain insurance coverage throughout the project.
• The contract includes provisions for changes to the work, including the process for submitting and approving change orders.
• The contract includes a termination clause, which outlines the circumstances under which the contract may be terminated.
• The project is expected to be completed within 163 days, with substantial completion by March 9, 2018, and final completion by March 16, 2018.