The Summit County Culvert Replacement and Maintenance Program is a contract for the replacement and maintenance of culverts in Summit County, Ohio. The contract includes the removal and replacement of culverts, pavement, and guardrail, as well as regrading and sediment removal. The contract has a completion date of October 30, 2020, and an engineer's estimate of $317,000.00. The contract was bid on by multiple vendors, including Spano Brothers Construction, Inc., Lockhart Concrete Co, Nerone & Sons, Inc., Cavanaugh Building Corporation, S.E.T., Inc., and Tri Mor Corp. The contract was awarded to one of these vendors, but the document does not specify which one.
• The contract includes the replacement of culverts, pavement, and guardrail
• The contract has a completion date of October 30, 2020
• The contract has an engineer's estimate of $317,000.00
• The contract was bid on by multiple vendors
• The contract was awarded to one of the vendors, but the document does not specify which one