The contract is for geothermal repair work on Capitol Blvd at the Boise River, specifically replacing existing 10" and 12" fiberglass geothermal lines with new 12" and 16" high-temperature HDPE Platinum Stripe pipes. The scope of work includes excavation, removing the existing fiberglass pipes, installing new HDPE pipes, setting a new 4'x6' vault in the greenbelt tunnel, reconnecting the new HDPE to the system, surface restoration, traffic control, dewatering, and related items. The City of Boise is the contracting agency, and the contract was awarded through a competitive bidding process.
• The contract involves geothermal repair work on Capitol Blvd at the Boise River.
• The scope of work includes excavation, pipe installation, and surface restoration.
• The City of Boise is the contracting agency.
• The contract was awarded through a competitive bidding process.
• The contract involves replacing existing fiberglass pipes with new HDPE pipes.
• The project requires traffic control, dewatering, and related items.