This contract awards a single‑vendor, fixed‑price construction effort to perform Phase I noise‑control tenant improvements at the AIDEA/AEA building in Anchorage, Alaska. The work includes selective demolition, asbestos‑abatement, new HVAC equipment, electrical upgrades, fire‑alarm system replacement, structural framing, acoustic ceiling installation, and interior finishes, all to be substantially completed by mid‑December 2018. The procurement was conducted through an open competitive bid, with Absolute Services, Inc. selected as the awardee. Key compliance requirements include adherence to OSHA/NEPA asbestos handling, NFPA fire‑alarm standards, and Alaska state wage rates.
• Scope: demolition, asbestos abatement, HVAC, electrical, fire‑alarm, structural, acoustic and finish work.
• Schedule: bids due Sep 28 2018; substantial completion Dec 12 2018; final completion Dec 19 2018.
• Financials: base bid $320,000; after 5 % Alaska preference adjusted bid $304,000 (estimated contract value ~ $300 k).