This contract concerns the replacement of a boiler system at the Transit Center, including two mandatory alternates for pump replacement and pump relocation. Two firms submitted competitive bids, with the lower‑priced bidder offering a total of $89,800 for all three line items, while the higher bidder’s total was $150,000. The work is a lump‑sum, competitive procurement.
• Scope: Remove and replace existing boiler; replace circulation pumps and housings; relocate pumps from overhead to floor‑mount.
• Procurement: Competitive bid (two vendors); “Bids Received” deadline March 6 2026.
• Financials: Base‑only bids range $52,400–$83,000; full‑scope bids up to $150,000.