This contract awards a design‑build team the renovation of the existing 3,500 sf community center at 881 Senoia Road, Tyrone, GA, including interior upgrades, ADA‑compliant ramp and parking, new flooring, cabinetry, bathroom fixtures, and related mechanical/electrical work, together with required permitting and inspections. The project is funded by the Town of Tyrone and will be completed under a fixed‑price lump‑sum contract.
• Scope: full architectural, structural, MEP design plus construction; remodel interior, add ADA ramp, install laminate flooring, cabinets, bathrooms, lobby glass.
• Schedule: bid deadline 02/04/2026; construction must be finished no later than 08/01/2026 (≈90 days from notice‑to‑proceed).
• Award: Blue Chip Builders selected with a base bid of $199,935; contract type is design‑build, firm‑fixed‑price.