The contract is for the Mather Airport General Aviation Apron Modifications, which includes pavement removal and replacement, striping removal and replacement, and storm drain enhancements. The engineer's estimate for the project is $4,563,700.00, with an additive bid alternate of $291,285. The contract was awarded to the apparent low bidder, Granite Construction Co, with a bid of $4,831,506.05. The project has a non-mandatory pre-bid conference and walk-through, and the contract documents are available for download.
• The project requires a Class A License.
• The project has a bid opening date of June 8, 2017.
• The project has a pre-bid conference and walk-through on May 18, 2017.
• The contract documents are available for download on the County of Sacramento's website.