The contract is for improvements to the WRF Administration Building HVAC system, including a new heat exchanger, replacement of selected undersized heat pumps, replacement of selected piping, and a new control system. The contract was awarded to Precision Mechanical, Action Mechanical, and Tessier’s, with base bids of $223,808.00, $192,500.00, and $243,703.00, respectively. The engineer's estimate for the project was $225,000.00.
• The project involves HVAC improvements
• The project includes a new heat exchanger and control system
• The project has a base bid range of $192,500.00 to $243,703.00
• The engineer's estimate for the project is $225,000.00