The contract modernizes three varsity athletic fields at Lynwood High School’s Imperial Campus, adding synthetic turf, lighting, fencing, and associated site improvements, and constructs a new one‑story team room and storage building. The work encompasses extensive civil‑site preparation, grading, drainage, irrigation, paving, utility connections, and compliance with prevailing‑wage, DVBE, and Community Workforce Agreement requirements. The project is funded by the district, will be executed under a lump‑sum award, and includes performance and payment bonds equal to 100 % of the contract amount.
• Scope: turf removal and installation, lighting, scoreboards, fencing, paving, team room/storage building, accessibility upgrades, and utility work.
• Schedule: 355‑day construction period from July 13 2026 to July 2 2027.
• Procurement: Formal Invitation to Bid, full‑open competition, with mandatory pre‑qualification, bid security (≥ 10 % of bid), and extensive bonding/insurance requirements.