The contract is for the replacement of the Harold and Van Mar Lift Station, which includes the installation of four submersible pumps, piping, fittings, and valves, as well as associated demolition, electrical, instrumentation, and site work. The contract was awarded through an Invitation for Bid (IFB) process, with a bid submission date of May 8, 2018. The bid tabulation section lists several companies that submitted bids, with Crossland Heavy Contractors being the apparent low bidder. The contract value is estimated to be around $877,000.
• The contract includes the installation of four submersible pumps, including guide rails and brackets.
• The contract includes the installation of an owner-supplied skid-mounted diesel pump.
• The contract includes piping, fittings, and valves, as well as associated demolition, electrical, instrumentation, and site work.
• The contract was awarded through an Invitation for Bid (IFB) process.
• The bid submission date was May 8, 2018.
• The contract value is estimated to be around $877,000.