This solicitation seeks a qualified contractor to fully rehabilitate the heating, ventilation, and air‑conditioning (HVAC) systems that serve the Air Traffic Control Tower (ATCT) at Toledo Express Airport. The work includes demolition of existing rooftop, air‑handling, condensing units, ductwork and associated controls, followed by installation of new HVAC equipment, humidification, and all required mechanical, electrical, plumbing, and fire‑protection interfaces. The contract is divided into a 252‑day procurement/fabrication phase and an 84‑day construction phase, for a total of 336 consecutive calendar days. Bidders must submit a 10 % bid bond or certified check, comply with Davis‑Bacon prevailing‑wage rules, and provide extensive documentation, including warranties, as‑built drawings, and required certifications.