This project calls for the complete relocation and upgrade of Sewage Pump Station 0382 in Miami, FL. The contractor must demolish the existing wet‑well and dry‑well structures, remove and salvage equipment, and construct new civil, mechanical, and electrical facilities at a new approved site. The scope includes design, permitting, by‑pass pumping, MOT traffic plan, storm‑water BMPs, installation of new pumps, piping, control panels, SCADA/RTU, and full testing/commissioning, followed by site restoration and landscaping.
• Demolition of existing pump station components, asbestos‑cement pipe removal, and disposal of hazardous material.
• Installation of new wet‑well, valve vault, two 15 HP submersible pumps, 8‑in. ductile‑iron force main, electrical service, SCADA/RTU, and associated civil works (concrete, asphalt, sod, landscaping).
• Provide uninterrupted by‑pass pumping and power, develop/maintain a Maintenance‑of‑Traffic plan, comply with storm‑water BMPs, and complete factory, on‑site, and system‑integration testing with all costs bundled in the bid.