The University of Toledo is seeking a qualified contractor to replace and modernize multiple elevators at the University Medical Center and Carlson Library. The work includes full demolition of existing elevator equipment, installation of new MAD‑brand traction and hydraulic elevators, associated fire‑stop sealing, electrical upgrades, waterproofing, and interior finishes. The contract is split into two general‑contract packages with optional alternates, and the overall project must be completed within 520 days after receipt of the Notice to Proceed.
• Scope covers removal of existing elevators, new MAD elevator installation, pit waterproofing, fire‑stop sealing, electrical panel and lighting upgrades, and interior finish work.
• Two bid packages: Package 101 (UMC – 3 patient‑transport side hospital elevators) and Package 102 (Carlson Library – 4 elevators). Optional alternates for raised panels, steel wraps, graphics, and debris removal.
• Contract value ≈ $2.74 M base; up to ≈ $2.94 M if all alternates are exercised. Contractor must meet Ohio prevailing‑wage, domestic‑steel, EDGE (≥5 % participation), and SUPR program requirements, and provide bonds, insurance, and certifications.
• Mandatory pre‑bid meeting on May 12 2026 (9 AM) with an on‑site walk‑through; questions due May 19 2026; bid deadline May 26 2026 2 PM EDT.
• Substantial completion required within 520 days after Notice to Proceed; multiple milestone dates tied to the NTP (e.g., 200‑day, 310‑day, 400‑day, 500‑day milestones).