The City of Boise is seeking a qualified contractor to design and construct a multi‑use pathway on the western side of Charles F. McDevitt Park, linking the existing northern trail to the parking‑lot pathways and installing two new light poles. The work includes earthwork, grading, concrete sidewalk installation, demolition of existing hardscape, utility (irrigation and lighting) installation, erosion‑control measures, and comprehensive landscape restoration.
• Civil‑engineering scope: grading, excavation, storm‑water BMPs, and concrete sidewalk (4 in. thick, 4,000 psi) with required joint and finish specifications.
• Utility scope: installation of two light poles, conduit, back‑flow devices, and an irrigation system (PVC, pressure‑tested, with seasonal adjustments).
• Environmental & landscaping scope: tree‑protection fencing, erosion & sediment control, soil amendment using on‑site soil and city‑provided compost, seeding/sod, and post‑construction landscape establishment.
• Project schedule: 61 calendar days (including 13 weather days) from anticipated Notice to Proceed on May 13 2026, with a liquidated‑damage rate of $500 per day for late completion.
• Mandatory requirements: 5 % bid security, electronic signature, Procore submittal management, Idaho Public Works licensing for any self‑performed plumbing/HVAC/electrical work, and compliance with ISPWC 2025 amendments.