The New York City Health + Hospitals (NYC H+H) is soliciting competitive sealed bids for a full‑scale renovation of the dental suite at its Gotham Vanderbilt Health Center (165 Vanderbilt Ave, Staten Island). The work includes demolition, structural metal work, MEP installations (hard‑piped nitrous‑oxide and oxygen, new plumbing, electrical, HVAC, fire‑alarm), new casework, dental chairs, finishes, ADA‑compliant restroom, and integration with existing building systems. All work must comply with FGI dental‑suite standards, NYC building codes, the NYC H+H Project Labor Agreement, prevailing‑wage requirements, and a 32 % M/WBE participation goal. Bids must be submitted by the PIN deadline, and only bidders who attend the mandatory pre‑bid meetings (March 12‑13, 2026) will be considered responsive.
• Scope covers demolition, mechanical, electrical, plumbing, fire‑alarm, casework, finishes, equipment installation, and associated coordination drawings.
• Project must be self‑performed (no subcontracting > 75 % without prior approval) and adhere to the NYC H+H PLA and prevailing‑wage rates.
• Mandatory after‑hours restrictions for noisy work, strict 72‑hour notice requirements for utility or disruptive operations, and monthly progress documentation are required.
• The contract will be awarded to the lowest responsive and responsible bidder; the schedule is 547 calendar days from Notice‑to‑Proceed.