The City of Sacramento is seeking a qualified contractor to replace the roof on Section 3 of the Public Safety Center, with two optional additive alternates (Sections 4 and 8). The work includes complete demolition of the existing roofing system, installation of new PVC/TPA membrane roofing, insulation, flashings, curbs, walkways, and associated structural modifications. The contract is valued at $300,000 and requires a 10 % bid bond, 100 % performance and payment bonds, and a minimum 5 % Local Business Enterprise participation. The project must be completed within 60 calendar days after the Notice to Proceed, with liquidated damages of $1,000 per day for delays.
• Scope covers full roof removal, new insulation, TPA membrane installation, flashings, curbs, walkways, and final finishes.
• Two additive alternates (Sections 4 & 8) may be awarded separately; they are priced in the bid but not required.
• Mandatory pre‑bid meeting on March 18, 2026 (non‑mandatory attendance) and sealed bids due April 1, 2026 at 2 PM at the City Clerk’s public counter.
• Requires 10 % bid bond, 100 % performance/payment bonds, 5 % LBE participation, and compliance with prevailing‑wage, insurance, and warranty provisions.