The City of Fayetteville is awarding a construction contract to replace and upgrade drainage, water, and sanitary sewer infrastructure along Tryon Drive. The contractor will install new reinforced‑concrete drainage piping and box culverts, replace an existing asbestos‑cement water main with a new 8‑in. ductile‑iron line, renew water‑service connections, install new sanitary‑sewer pipe and manholes, perform extensive site‑work (excavation, grading, erosion control, traffic control), and complete associated landscaping and pavement work. The contract is a stipulated‑price, EJCDC‑based agreement with a 480‑day performance period, liquidated damages of $1,000 per day for late completion, and a required performance and payment bond.
• Install ~1,250 ft of reinforced‑concrete drainage pipe and ~400 ft of box culverts.
• Remove existing asbestos‑cement water main and install ~2,000 ft of new 8‑in. PC‑350 ductile‑iron water main, plus related valves, fittings, and meter work.
• Replace/construct sanitary‑sewer pipe, manholes, cleanouts, and related utilities; perform hydro‑static testing and disinfection.
• Conduct full site‑work: clearing, grading, back‑fill, erosion‑control, traffic‑control plans, pavement removal/replacement, curb‑and‑gutter, and landscaping (seeding/sod).
• Provide required documentation, testing, and warranty compliance; adhere to strict work‑hour windows, utility‑coordination notices, and vibration‑monitoring requirements.