The project involves replacing the existing life‑safety generator and automatic transfer switch (ATS) for the Mathematical Sciences Building at Kent State University. The work includes demolition of the old generator, installation of a new 350 kVA diesel generator with a 12‑hour fuel tank, concrete pad construction, fencing, conduit and wiring upgrades, and integration with building systems such as the elevator controller. Three alternates are offered: removal of the existing generator ($25,000), provision of a temporary generator cabinet ($15,000), and a credit for using non‑fire‑rated conduit ($‑10,000). The contract is subject to Ohio prevailing‑wage, domestic‑steel, EDGE diversity, and SUPR program requirements, and requires a hard‑copy bid guaranty and performance bond within three days of bid opening.
• Electrical scope: generator, ATS, switchgear, fire‑rated conduit, control wiring, and elevator integration.
• Civil scope: site grading, concrete pad, and fencing.
• Compliance: Ohio prevailing‑wage, domestic‑steel, EDGE 5 % diversity goal, drug‑free certification, and mandatory bid guarantees.
• Schedule: Pre‑bid meeting 20 Oct 2026, bid deadline 30 Oct 2026, anticipated award 14 Dec 2026, NTP 11 Jan 2027, contract completion 420 days thereafter.