This $4 million, Labor & Materials solicitation covers two major waterfront projects at Manson, Washington: a breakwater replacement and a dock replacement. The work involves full demolition, procurement, and installation of steel piles, floating breakwater units, gangways, pump‑out stations, lighting, and related electrical components. Three regional contractors submitted bids ranging from $3.41 M to $3.97 M, but the bids were ultimately rejected. The agency seeking a qualified contractor is the Chelan Public Utility District, with contact Tammy Harn for any inquiries.
• Scope includes removal of existing marina structures, installation of new steel‑galvanized pipe piles, fiberglass pile caps, floating breakwater, aluminum gangway, and pump‑out station.
• Additional work on the Old Mill Park Dock involves steel‑framed platforms, new dock floats, revised layout, and associated lighting/electrical upgrades.
• Estimated project cost $4 M; bids received between $3.41 M and $3.97 M; status: Bids Rejected (no award yet).
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.