The University of Louisville is seeking a qualified contractor to replace the existing 350 kW emergency generator at the Ekstrom Library with a new 400 kW owner‑furnished unit and to perform all associated electrical work, including demolition of existing equipment, installation of a new 600 A transfer switch, conduit, grounding, and emergency‑power systems. The project must be coordinated to minimize downtime, adhere to Kentucky building and fire codes, and be completed within a tight summer schedule. Bids are due electronically by 2 PM EST on 27 Mar 2026, with work slated to begin 11 May 2026 and finish by 3 Aug 2026. The award will be based on the lowest responsive and responsible bid, subject to bonding, insurance, and workers‑comp requirements.
• Replace the 350 kW diesel generator with a 400 kW generator (owner‑furnished, contractor‑installed).
• Provide new 600 A automatic transfer switches, upgrade electrical panels, conduit, grounding, and emergency lighting controls.
• Perform demolition of existing generator, fuel tank, switchgear, and related infrastructure; restore finishes and coordinate phased power cut‑over.
• Meet all applicable codes (Kentucky Building Code 2018, NFPA 70 2023, NFPA 110, etc.) and submit required shop drawings, cost breakdowns, and warranty documentation.
• Must supply bid bond (5 % of bid), performance and payment bonds, workers‑comp affidavit, and certificates of insurance as part of the bid package.