The City of Palm Bay is seeking bids for the rehabilitation of a 500,000 gallon ground storage tank at the North Regional Water Treatment Plant. The scope of work includes mobilization and demobilization, demolition, power washing and cleaning, concrete rehabilitation, and painting and coating. The contract has an engineer's estimate of $275,000. The successful bidder will be required to complete the work within 120 days, with a maximum of 75 consecutive calendar days for the tank to be out of service.
• The contract includes various line items such as mobilization and demobilization, demolition, power washing and cleaning, concrete rehabilitation, and painting and coating.
• The engineer's estimate for the project is $275,000.
• The successful bidder will be required to complete the work within 120 days.
• The tank can only be out of service for a maximum of 75 consecutive calendar days.