This contract is a solicitation for the complete demolition and removal of the historic Lions pedestrian bridge in Greenfield Lake Park, Wilmington, NC. The work includes dismantling all bridge components, handling hazardous materials such as asbestos and lead‑based paint, hauling and disposing of debris at an EPA‑approved landfill, protecting live trees, restoring the site with grading and seeding, and coordinating with multiple utilities. The City requires compliance with OSHA, EPA, and state environmental regulations, a 14 % MWBE subcontracting goal, and a one‑year warranty on workmanship. The maximum contract value is $98,000, with a 90‑day construction schedule and liquidated damages of $230 per day for overruns.
• Demolition of a 120‑ft timber‑pile bridge, including pile removal or cut‑off.
• Hazardous‑material abatement (asbestos, lead‑based paint) by accredited firms.
• Site restoration, utility coordination, and strict environmental controls (debris booms, turbidity curtains).