This contract is for the Lake Havasu City Probation/County Attorney Office Tenant Improvement project, which includes demolition, new walls, new finishes, mechanical, plumbing, and electrical improvements. The project has an estimated value of $117,000 and a construction allowance of 60 days from Notice to Proceed. The contract was awarded to T.R. Orr, Inc. through an Invitation for Bid process. The project is being funded with American Rescue Plan Act (ARPA) funds and is subject to Federal regulations. The contract includes requirements for insurance, bonding, and performance and payment bonds. Some key points to note are:
* The project includes a 1,300 SF interior remodel for Probation and a 520 SF interior remodel for County Attorney.
* The scope of work includes demolition, new walls, new finishes, mechanical, plumbing, and electrical improvements.
* The construction allowance is 60 days from Notice to Proceed.
* The contract was awarded to T.R. Orr, Inc. for a total bid amount of $117,000.
* The contract includes requirements for insurance, bonding, and performance and payment bonds.
* The project is being funded with American Rescue Plan Act (ARPA) funds and is subject to Federal regulations.
Some potential risks or challenges associated with this contract include:
* Delays in the construction process due to unforeseen site conditions or changes in the scope of work.
* Issues with the quality of work or materials used by the contractor.
* Difficulty in coordinating with the County's Facilities Division to schedule work and ensure access to the site.
* Potential changes in the funding or regulatory requirements for the project.
* Risks associated with the use of ARPA funds, such as compliance with Federal regulations and potential audits.