This contract is for the provision of steel substation structures. The City of Roseville published an RFQ and received bids from multiple vendors. The contract was awarded to DIS-Tran Steel Fabpole and M.D. Henry Company. The scope of work includes the supply of steel substation structures. Key points to consider are the bid bond requirement, the product total, and the addendum.
• The bid bond is required for this contract.
• The product total for the contract is $321,586.00 and $575,942.00 for the two vendors.
• An addendum was issued for the contract, which is available for download.
This contract may be of interest to companies that specialize in steel fabrication and supply, particularly those with experience in providing substation structures.