The Hot Water Utilidor Project involves the removal and replacement of hot water piping and valves throughout the California Polytechnic State University campus in San Luis Obispo, California. The project includes the installation of new welded steel piping, valves, anchors, concrete flatwork, asphalt paving, and minor concrete structures. The construction estimate for the base bid is $4,500,000, and the construction estimate for the additive alternates is $3,800,000 for alternates 1-4 and $1,800,000 for alternates 5 and 5.1. The project was awarded to Maino and Boneso Bros. for a total award amount of $7,289,694.
• The project involves the replacement of hot water piping and valves throughout the campus.
• The construction estimate for the base bid is $4,500,000.
• The construction estimate for the additive alternates is $3,800,000 for alternates 1-4 and $1,800,000 for alternates 5 and 5.1.
• The project was awarded to Maino and Boneso Bros. for a total award amount of $7,289,694.
• The project includes the installation of new welded steel piping, valves, anchors, concrete flatwork, asphalt paving, and minor concrete structures.