The contract involves the superstructure replacement of Montgomery County Bridge 268, located on Easton Road over Tacony Creek in Cheltenham Township. The project includes replacing the existing single span non-composite adjacent box beam structure with a single span composite prestressed adjacent plank beam structure, as well as other associated work such as full depth approach work, utility relocation, and more. The contract was posted on June 1, 2018, and the bid submission deadline was June 29, 2018.
• The contract includes various line items such as Class 1b Excavation, Class 3 Excavation, Geotextile, and more.
• The contract has a total value of approximately $958,000 to over $1.17 million, depending on the bidder.
• The contract was awarded to JPS Construction, although the exact award amount is not specified in the provided text.