This contract concerns the removal of two damaged barge‑fleet mooring “dolphin” piles and the installation of new 42‑inch steel pipe piles at the McDuffie Terminal in Mobile, Alabama. The work includes full‑depth removal, disposal, splicing of piles up to 80 ft, and application of a two‑coat protective paint system (safety‑yellow macropoxy on the top 25 ft and coal‑tar epoxy on the next 15 ft). The contractor must supply all labor, equipment, and supervision, hold the required Alabama General Contractor license, provide performance and labor‑&‑materials bonds equal to 100 % of the contract price, and meet extensive insurance and tax‑exemption requirements. The project schedule is limited to 30 calendar days of on‑site work, with liquidated damages of $500 per day for overruns.