The North Creek Trail Phase I project is a multi‑disciplinary public‑works construction effort to improve the trail corridor from SR 524 to Sprague Drive in Snohomish County, WA. The work includes extensive site preparation, earthwork, grading, storm‑sewer and water‑line installation, concrete boardwalk and retaining‑wall structures, asphalt paving, erosion‑control measures, native‑plant landscaping, and comprehensive traffic‑control and signage installations. The contract was awarded to Rodarte Construction Inc. under a firm‑fixed‑price arrangement, with a 5 % bid bond requirement and mandatory Under‑Utilized Disadvantaged Business Enterprise (UDBE) participation.
• Scope covers clearing & grubbing, excavation, utility relocations, storm‑sewer pipe (CPE and ductile‑iron), water‑main work, boardwalk structures, detention tanks/vaults, HMA paving, erosion‑control blankets, check dams, and extensive planting of native species.
• Engineer’s estimate cited at $8,335,000; bid totals around $8.2 million.
• Requires compliance certifications (federal debarment, non‑collusion, wage‑payment statutes, UDBE utilization) and submission of a 5 % performance/payment bond.