The contract is for improvements to Nashville Avenue in Port Arthur, Texas. The project involves paving improvements, including the removal and disposal of existing asphalt surface, base, and subbase, and the installation of new reinforced concrete pavement, limestone base material, and hot-mix asphalt surface course. The contract also includes the adjustment of manholes, water valves, and storm pipe, as well as the installation of new curb inlets and wheelchair ramps. The vendors which this contract was awarded to are Gulf Coast a CRH Company, Brystar Contracting, Inc., and BDS Constructors, LLC. (Dba MK Constructors).
• The contract has a total of 23 items, including mobilization and demobilization, removal and disposal of existing asphalt surface, base, and subbase, and the installation of new reinforced concrete pavement, limestone base material, and hot-mix asphalt surface course.
• The contract includes the adjustment of manholes, water valves, and storm pipe, as well as the installation of new curb inlets and wheelchair ramps.
• The vendors submitted bids for the contract, with Gulf Coast a CRH Company submitting a bid of $913,289.50, Brystar Contracting, Inc. submitting a bid of $1,068,320.00, and BDS Constructors, LLC. submitting a bid of $1,245,417.50.