The AML Project 16 O, Phase 5, McIntosh Pit Backfill Project involves the backfilling of the McIntosh Pit. The project was awarded to Summit Excavation & Grading, LLC for a total bid of $1,584,050.00. The project requires the contractor to perform the work in accordance with the specifications and addenda provided. The contractor must also provide a 10% bid bond and comply with all applicable laws and regulations.
• The project involves backfilling the McIntosh Pit
• The contractor must provide a 10% bid bond
• The contractor must comply with all applicable laws and regulations
• The project was awarded to Summit Excavation & Grading, LLC for a total bid of $1,584,050.00
• The project requires the contractor to perform the work in accordance with the specifications and addenda provided