The City of Ridgefield has awarded a contract to Wallis Engineering for the provision of preconstruction design services and selected construction support services for three stormwater projects downtown. The scope of work includes tasks such as project management, data collection, preliminary permitting, and infiltration testing. The contract has a duration of 22 months and a total value of $234,850.78. The project aims to address nuisance flooding, reduce maintenance demands, and improve the treatment capacity of the City's stormwater infrastructure. Some of the key deliverables include a cultural resources survey report, a stormwater design report, and a preliminary design for the selected alternative. The contract also includes a fee estimate and a rate schedule for the services provided by Wallis Engineering.
• The contract includes tasks such as project management, data collection, preliminary permitting, and infiltration testing.
• The scope of work has been altered to reflect the City's preferred scope changes made during billing.
• The project aims to address nuisance flooding, reduce maintenance demands, and improve the treatment capacity of the City's stormwater infrastructure.
• The contract has a duration of 22 months and a total value of $234,850.78.
• The project includes a cultural resources survey report, a stormwater design report, and a preliminary design for the selected alternative.