Awarded vendors
- Freeman Concrete Construction, LLC
- O'Donnell & Sons Construction Co., Inc.
- McAnany Construction, Inc
- Kansas Heavy Construction, LLC
- Bettis Asphalt & Construction, Inc.
Description
The contract involves the Kansas Avenue Arterial Mill and Overlay project, which includes milling and asphalt resurfacing, subgrade repair, concrete curb and gutter replacement, sidewalk and ADA sidewalk ramp replacement, driveway replacement, storm sewer inlet and pipe improvements, pavement markings, and permanent signing. The project is located on Kansas Avenue and Southgate Street in Olathe, Kansas. The contract was awarded through a competitive bidding process, with five companies submitting bids. The contract value is estimated to be around $1.3 million. Key aspects of the project include:
• Milling and asphalt resurfacing of approximately 23,848 square yards
• Installation of 2" modified superpave asphaltic concrete surface
• Replacement of concrete curb and gutter, sidewalks, and driveways
• Installation of storm sewer inlets and pipes
• Pavement markings and permanent signing
The project requires the contractor to mobilize to the site, perform the necessary work, and demobilize upon completion. The contract also includes a contingency allowance for unexpected expenses.