The City of Prescott is undertaking a municipal water‑infrastructure project to extend a 12‑inch water main through Zone 52, including installation of ductile‑iron and HDPE pipe, valve assemblies, PRV stations, demolition of an existing tank and booster pump, and associated roadway and site restoration. The work is to be performed under a fixed‑price unit‑price contract with a 300‑day construction window after the Notice to Proceed. CLM Earthmovers LLC was selected as the successful bidder with a bid of approximately $1.52 million.
• Scope: ~4,700 LF of 12‑in. DIP, ~230 LF of 12‑in. HDPE, demolition of tank/booster, roadway improvements, SWPPP compliance, and testing/commissioning.
• Schedule: Bid opening 17 Oct 2024; award 19 Nov 2024; NTP expected early Dec 2024; completion anticipated early Oct 2025 (300 days).
• Requirements: Arizona A‑General Engineering license, 10 % bid guarantee, performance/payment bonds, insurance minimums, and strict utility‑coordination, traffic‑control, and environmental‑protection procedures.