The contract is for the Aging Facilities Project: Ceilings, which involves ceiling replacements at various elementary schools in the Olathe Public Schools USD #233 district. The contract was awarded to multiple vendors, including The Wilson Group, Inc., MCM Project Management LLC, and TPC Interiors, Inc. The scope of work includes interior ceiling replacements at Black Bob Elementary School, Heritage Elementary School, and Sunnyside Elementary School. The contract has a base bid of $412,731.62, $258,381.00, and $633,630.00 for each vendor, respectively.
• The contract has a liquidated damages clause of $1,000 per calendar day if the project is delayed beyond the contracted completion date.
• A non-mandatory pre-bid site visit was held on February 6, 2024.
• The contract requires a bid bond of 5% of the total bid amount.
• The contract is subject to approval by the Board of Education.