The contract is for lead abatement services at 708 Aberdeen St. in Akron, Ohio. The work includes enclosing front porch knee walls, railings, ceiling, floor, beams, and columns with vinyl or aluminum coil stock, as well as prep and application of an ODH-approved encapsulant in the basement stairwell. The contractor must follow HUD Lead Safe Housing requirements and COVID-19 protocols. The estimated cost of the project is $37,000, and bids over 10% of the estimate may not be considered. The project must be completed within 30 days of signing the contract.
• Lead abatement services
• Enclosing front porch knee walls, railings, ceiling, floor, beams, and columns
• Prep and application of an ODH-approved encapsulant in the basement stairwell
• Following HUD Lead Safe Housing requirements and COVID-19 protocols
• Estimated cost: $37,000
• Project completion timeframe: 30 days