The North Lightning Complex MBGR Replacement project involves the removal of metal beam guardrail, installation of Midwest Guardrail Systems, traffic control, grading, and signage. The project is located in Butte County, California, and the engineer's estimate is $132,100.00. The contract was awarded to Coral Construction Company and Dirt & Aggregate Interchange, Inc. The scope of work includes furnishing all labor, tools, materials, equipment, and incidentals necessary to complete the project as shown on the plans.
• The project requires compliance with the California Department of Transportation 2018 Standard Specifications.
• The project involves the removal and relocation of roadside signs.
• The project requires the installation of Midwest Guardrail Systems, including end anchor assemblies and terminal end sections.
• The project requires the services of a contractor-supplied biologist.