The Biofilter Media Replacement Project involves the rehabilitation of biofilters, including removal and replacement of biofilter media, lava rock, plastic screens, and other components. The project has an expected duration of 150 calendar days and a total bid price of approximately $599,495. The contract was awarded to four different vendors: Gateway Pacific Contractors, Santos Excavating, R&R Horn, and Valentine Corp. The project includes various work items, such as membrane liner repair and unforeseen conditions and owner-requested change allowances.
• The project requires the removal and replacement of biofilter media, lava rock, and other components.
• The project has an expected duration of 150 calendar days.
• The total bid price for the project is approximately $599,495.
• The contract was awarded to four different vendors.
• The project includes various work items, such as membrane liner repair and unforeseen conditions and owner-requested change allowances.