The contract is for the installation of 8-inch water and sewer along Fox Rd. and installation of 8-inch water in Berglund Rd. The project is partially funded from a developer settlement. The bid results show three bidders, with base bids ranging from $405,091.93 to $438,444.75. The engineer's estimate is $325,000.00. Key aspects of the contract include the installation of water and sewer lines, and the project's funding.
• The project involves the installation of 8-inch water and sewer lines.
• The project is partially funded from a developer settlement.
• The bid results show three bidders, with base bids ranging from $405,091.93 to $438,444.75.
• The engineer's estimate is $325,000.00.