Awarded vendors
- Miles Excavating, Inc.
- Freeman Concrete Construction, LLC
- Kansas Heavy Construction, LLC
- Linaweaver Construction, Inc.
Description
The contract is for the 2014 Cedar Creek Street Rehabilitation for 111th Terrace and Whitetail Lane, which involves the construction of approximately 6522 square yards of full depth portland cement concrete pavement removal and asphaltic concrete pavement replacement, 4100 linear feet of concrete curb and gutter, sidewalks and sidewalk ramps. The contract was awarded through a competitive bidding process, with multiple vendors submitting bids. The successful bidder will be required to furnish and pay satisfactory performance and payment bond or bonds. The contract also includes a bid alternate for Whitetail Lane.
• The contract involves excavation and grading, subgrade repair, removal of existing concrete pavement and sidewalks, installation of new asphaltic concrete pavement, concrete sidewalks, and underdrain.
• The contract requires the successful bidder to provide a satisfactory bid bond, performance bond, and payment bond.
• The contract includes a bid alternate for Whitetail Lane, which involves additional work such as excavation and grading, subgrade repair, and installation of new asphaltic concrete pavement.
• The contract is subject to the terms and conditions outlined in the contract documents, including the plans, specifications, and general conditions.
• The City of Olathe reserves the right to reject any or all bids and to waive any informality in the bidding.