Awarded vendors
- Dakota Barricade
Description
The 2020 Lane Line Painting project is an annual city-wide lane line repainting project that includes spring repainting of existing lane, edge, and center lines on City streets and fall repainting with a second coat on busiest arterial and collector roadways. The project was awarded to Dakota Barricade with a base bid of $121,600.00 and an alternate bid of $136,300.00. The engineer's estimate for the project was $102,000.00. The project is expected to cost around $120,000.00. Some key features of the project include:
• Annual city-wide lane line repainting
• Spring repainting of existing lane, edge, and center lines
• Fall repainting with a second coat on busiest arterial and collector roadways
• Awarded to Dakota Barricade
• Base bid of $121,600.00
• Alternate bid of $136,300.00
• Engineer's estimate of $102,000.00
• Expected cost of around $120,000.00