The City of Goodyear has awarded a contract to TF Contracting Services, LLC, for the Pima Waterline Repair project. The contract amount is $73,346.66, and the project involves excavating and tying in a 12" watermain on Pima Road and excavating and completing a point repair at a location to be determined by the City of Goodyear. The project includes all associated potholing, asphalt removal and replacement, and traffic control. The contract was awarded through a job order contract, and the City of Goodyear is responsible for managing the project. The key aspects of this contract include the scope of work, contract amount, and project timeline.
• The scope of work includes excavating and tying in a 12" watermain on Pima Road and excavating and completing a point repair at a location to be determined by the City of Goodyear.
• The contract amount is $73,346.66.
• The project timeline is 49 days, starting from May 12, 2025, and ending on June 30, 2025.
• The contract was awarded to TF Contracting Services, LLC, through a job order contract.
• The City of Goodyear is responsible for managing the project.