The Town of Prescott Valley is seeking bids for the construction of the HWY 69/169 Roundabout Waterline Relocation Project. The project involves site preparations, removal of existing manholes, installation of new sewer and water mains, and site restoration. The contract was awarded to multiple vendors, including EARTH RESOURCES CORPORATION, JUD CO LLC, ASPHALT PAVING & SUPPLY, INC., CLM EARTHMOVERS LLC, PRONGHORN SERVICES LLC, and STANDARD CONSTRUCTION COMPANY, INC. The bid tabulation document lists the prices and quantities for each item of work.
• The project includes the installation of 200 lf of 8-inch sanitary sewer main and two manholes.
• The project includes the installation of 220 lf of 8-inch water main and 400 lf of 12-inch water main.
• The project includes the removal of existing 12-inch water main and valves.
• The project includes site restoration and testing of new sewer and water mains.
• The contract was awarded based on a competitive bidding process.
• The bid tabulation document lists the prices and quantities for each item of work.
• The project is located in Prescott Valley, Arizona.
• The project is being managed by the Town of Prescott Valley.
• The point-of-contact person for the project is Bill Osborne, who is the Capital Projects Coordinator for the Town of Prescott Valley.