This contract awards a lump‑sum, medium‑voltage electrical upgrade for the Four Rivers Sanitation Authority’s co‑generation plant in Rockford, Illinois. The work replaces two medium‑voltage feeders, upgrades switchgear, installs new underground conductors, adds four MV transformers, and provides temporary power solutions to keep critical facilities online during construction. The project must be completed within roughly 540 days, with strict sequencing requirements to maintain power continuity for the administration building, dewatering building, and the 3 MW co‑generation system.
• Scope: Replacement of MV feeders (F‑2, F‑7), installation of pad‑mounted and metal‑enclosed MV switchgear, four MV transformers, underground duct banks, and associated site/roadway work.
• Constraints: At least one feeder must stay energized at all times; additional standby generators (660 kW and 800 kW) must be provided by the contractor.
• Schedule: Pre‑bid meeting on April 1 2026, bid opening/closing on April 15 2026, substantial completion required within 540 days of contract award.