The contract involves the rehabilitation of Kelly Ridge Road ER, including clearing and grubbing, traffic control, asphalt concrete dig outs, and pavement markings. The engineer's estimate for the project is approximately $341,000. The contract was awarded through a competitive bidding process, with five bidders submitting proposals. The successful bidder, likely Franklin Construction, Inc., had a bid amount of $260,260.00, which is approximately 23.68% below the engineer's estimate.
• The project involves multiple components, including traffic control, clearing and grubbing, and pavement markings.
• The contract was awarded through a competitive bidding process.
• The successful bidder had a bid amount significantly below the engineer's estimate.
• The project is expected to start in early August 2020.
• The contract duration is not specified in the provided text.