The 2013 Local and Collector Mill & Overlay project involves the construction of local residential asphalt streets in Olathe, Kansas. The project includes milling and resurfacing of existing streets, removal and replacement of concrete curb and gutter, installation of ADA sidewalk ramps, and other related work. The contract was awarded through a competitive bidding process, with five vendors submitting bids. The contract value is estimated to be around $1 million to $1.3 million, based on the engineer's estimate and the bids submitted by the vendors. The project is expected to be completed within a few months, although the exact duration is not specified.
• The project includes approximately 66,371 square yards of 2" depth full width milling and placement of 2" asphalt surface.
• The project includes 71 ADA sidewalk ramps, sidewalk removal and replacement, and 18,982 linear feet of spot curb replacement.
• The contract requires the contractor to furnish and pay for satisfactory performance and payment bonds.
• The City of Olathe reserves the right to reject any or all bids or to waive any informality in the bidding.