This contract calls for the complete removal and replacement of three major mechanical systems at the Adult Detention Facility Annex in Wichita, Kansas: a comfort‑heating boiler, a domestic hot‑water heater, and a hot‑water storage tank, along with associated pump stations and recirculating pumps. The solicitation was issued by Sedgwick County and awarded to Kruse Corporation on a lump‑sum basis after a full and open competitive bidding process.
• Scope: Mechanical demolition and installation of a new boiler, water heater, and storage tank, including required electrical work, Schedule 40 condensate piping, and an emergency‑stop switch.
• Award: Kruse Corporation received the contract for $144,885 (lowest responsive bid).
• Procurement: Full and open competition with a bid‑bond requirement (5 % of bid) and mandatory acknowledgment of addenda; the award was approved by the Board of County Commissioners.