This contract is for the monumental signage phase II project at New Mexico State University. The project involves the selective demolition and new installation of six monumental signs in their respective locations. The contract was awarded to ESA Construction, Inc. with a total bid of $131,800.00. The project must be completed within 90 calendar days from the notice to proceed. The contract includes provisions for liquidated damages in case of late completion. The contractor must also comply with various laws and regulations, including the New Mexico Public Works Apprenticeship and Training Act and the New Mexico Workers' Compensation Act.
• The contract includes a base bid and three alternates.
• The contractor must provide a 5% bid bond and a performance bond.
• The contract includes provisions for subcontractors and their listing.
• The contractor must comply with the New Mexico Department of Labor's wage rates.
• The contract includes provisions for equal employment opportunities and non-discrimination.
• The contractor must provide insurance and bonding as required by the contract.