The contract is for the Miller Station Road Culvert Repairs project, which includes the replacement of a 24-inch CMP pipe culvert, rehabilitation of a 72-inch diameter concrete pipe culvert, construction of two concrete headwalls, and other related work. The project has a cost estimate of $210,000. The contract was awarded to Triangle Contracting, LLC for $241,820.00. The project requires bidders to be pre-qualified with the Department of Public Works.
• The project involves culvert repairs and rehabilitation
• The project requires pre-qualification with the Department of Public Works
• The contract was awarded for $241,820.00
• The project includes construction of concrete headwalls and stream diversion
• The project requires stabilization of all disturbed areas and maintenance of stream flow