The contract is for the replacement of select condensate mains throughout multiple spaces of the Memorial Fieldhouse. The project includes demolition, condensate piping, installation of condensate return pumps, and reinsulating previously abated piping. The estimated project completion date is August 1, 2026. The contract was awarded to three vendors: JC Construction & Design, 3 Adventure Construction, and GH Phipps Wyoming. The bids ranged from $718,000.00 to $778,000.00.
• The project involves replacement of condensate mains in the Memorial Fieldhouse.
• The project includes demolition, condensate piping, and installation of condensate return pumps.
• The project is expected to be completed by August 1, 2026.
• The contract was awarded to three vendors.
• The bids ranged from $718,000.00 to $778,000.00.